Scheduling an Installation
GEORGIA FLOORS new computerized scheduling system is simply called “The Scheduler”. The scheduler offers screens that allow installation and sales personnel to add jobs based on labor availability, sort through jobs by builder or salesperson in order to schedule labor more efficiently, and provide daily or weekly job reports that can be e-mailed within the company or to our clients.
We have ample installation manpower available to handle all of our customers’ needs. Floor covering installations should be scheduled at least 6 to 10 workdays in advance to ensure that we can effectively accommodate your requirements.
Of course, if you have any last minute emergencies, please contact your Account Manager and we will make every effort to rise to the task.
Allocation of Men and Materials to a New Installation Request
Builder Requests
Work to Be Done… Uncommitted Manpower Available…
Today 5%
in 1 working day 10%
in 2 working days 15%
in 3 working days 20%
in 4 working days 25%
in 5 working days 30%
in 6 working days 40%
in 7 working days 50%
in 8 working days 70%
in 9 working days 90%
in 10 working days 99%
Typical sequence of steps from order placement to installation:
Day 1: Builder calls in to schedule installation and confirms selection
Day 2: House is measured and quantities calculated
Day 3: Installation order is entered into data processing system, and job is posted on schedule board
Day 4: Material order to supplier is placed and potential back orders identified
Day 6 (pm):
Day 7: Materials received from supplier and entered into inventory
Day 8 (am):
Materials assigned to work order and staged for delivery Job shipped for installation